Orpheus workspace — M1 Pacific Upgrade — C201 pavement pricing and EOT

Interactive preview — illustrative project data, canned responses. Get early access →
C201 pavement pricing & EOT
M1 Pacific Upgrade · 5 indexed · 1 processing
Today · 9:14 AM
Reece Estimator9:14 AM

Price the C201 pavement — 40 MPa, SL82 mesh, urban crew, at SEQ base 2026-Q1.

Orpheus Cost · first principles9:14 AM

Here's a first-principles build-up for the C201 pavement, priced against your QLD civil rate library at SEQ 2026-Q1 rates and your Class 2 on-cost settings. Quantities are pulled from the indexed BOQ.

Rate build-up · C201 pavementClass 2 control · SEQ · 2026-Q1
Rate
$184.60/m²
Total · 2,400 m²
$443,040
Subgrade trim & prepare2,400 m²$11.60
40 MPa N-class concrete0.153 m³/m²$49.88
Place, screed, finish & cureUrban crew$24.00
SL82 mesh — supply & fix4.0 kg/m²$12.80
Edge formwork, joints & dowels$18.40
Testing, line-marking & sundries$22.92
Direct cost$139.60
Prelims & margin24.4% on sell$45.00
Rates traced to Cost DB · QLD Civil · quantities from M1-BOQ-Rev C.xlsx. Every line is editable.
Reece Estimator9:21 AM

Good. Now draft our EOT position for the 12-day rebar delay under AS 2124 cl 35.5.

Orpheus Contracts & commercial9:21 AM

I've prepared an EOT position from AS2124 Contract.docx and the Baseline Programme.xer. The rebar delay sits on the critical path — float is currently −8 days before recovery — so lodging the cl 35.5 notice inside the time bar is the priority.

EOT position · EOT-012AS 2124 · rebar delay (+12d)
cl 46.1 notice due — 14 Aug 20269 days left
Delay
+12d
Float
−8d
EOT sought
12d
Entitlement — Time: claimable under cl 35.5 (delay beyond reasonable control). Cost: weak — a supplier delay generally sits with the Contractor under cl 36; scope prelims only unless principal-caused.
Programme impact · critical-path fragnet
Rebar delivery+12d
Footing P12 pour+7d
Deck preparation+4d
Pavement handover0d
Linked evidencePhoto log (12) · supplier records · geotech record · programme fragnet above
QuantumTime-related prelims for the 12-day extension. Direct delay costs not scoped — see entitlement.
Drafted for your review — clause citations link back to AS2124 Contract.docx. Verify before issuing. Not legal advice.
Reece Estimator9:23 AM

If we can't lodge in time, what's our recovery position on the programme?

Orpheus Programme
Reading Baseline Programme.xer · running critical-path recovery
AS 2124 · SEQ · 2026-Q1
Orpheus drafts for your review — outputs land as .xlsx, .docx and .xer, traceable to your files.